B2039 Ockham Road North: Planned closures - 22 July to 3 August and 19 August to 6 October

Balfour Beatty advise

These closures are to enable Affinity Water to undertake water main works and so that they can make alterations to Ockham Park roundabout approach.

For the first closure, the northbound B2039 Ockham Road North will be closed over a distance of about ⅓ km on its approach to the Ockham Park roundabout. The closure will last for 2 weeks from Monday 22 July until Saturday 3 August. During this time, it will be possible to leave Ockham Park roundabout heading south towards Ockham and Horsley but not travel in the opposite direction.

The diversion will be via Ockham Road North to Forest Road and then left onto Old Lane, left onto the southbound A3 and leaving the A3 at the B2215 Ripley slip road to reach the Ockham Park roundabout.

For the second closure, the northbound B2039 Ockham Road North will be closed in both direction over a distance of about ⅓ km on its approach to the Ockham Park roundabout as will the entire roundabout. The closure will take place between 10pm and 5.30am (weeknights only) for 2 weeks from Monday 22 July until Saturday 3 August

The diversions for this closure are:

For the A3 south bound, traffic will be to remain on the A3 to the Burpham Junction and return via the A3 North Jacobs Well exiting the A3 North at the B2215 Ripley

For traffic from Ripley, will be via the B2215 Portsmouth Road to the A247 Clandon Road and the A3 South to Burpham and return via the A3 North Jacobs Well to the M25 J10.

For traffic exiting Mill Lane, will be to turn left only and travel to the M25 J10 and return via the A3 south joining the diversion for the A3 south slip road

The third closure will be put in place once SGN have completed gas work on the A247 Clandon Road.   

The northbound B2039 Ockham Road North over a distance of about ⅓ km on its approach to the Ockham Park roundabout will be closed again. This closure will last for 7 weeks from Monday 19 August until Sunday 6 October. During this time, it will be possible to leave Ockham Park roundabout heading south towards Ockham and Horsley but not travel in the opposite direction.

For the most up to date information on the project please visit: www.nationalhighways.co.uk/m25j10.