Reminder : M25 junction 10/A3 Wisley interchange | Upcoming M25 Closure | Friday 12 July to Monday 15 July

M25 Closure

The next closure will be in place from 9pm Friday 12 July until 6am Monday 15 July.

Part of the M25 is closing to lift 68 concrete beams, each weighing 16 tonnes, and another four beams weighing 40 tonnes into place for the new western gyratory bridge.

To safely complete this, a full weekend closure of the M25 between Junctions 10 (Wisley) and 11 (Chertsey) in both directions is required.

Only travel if necessary.

While the M25 is closed between junctions 10 A3 (Wisley) and 11 A320 (Chertsey), motorists travelling clockwise will be diverted from the M25 at junction 10 to use the A3 northbound travelling via the A245 at Painshill and the A320 to rejoin the M25 at junction 11.

Motorists travelling anti-clockwise will be diverted from the M25 at junction 11 to join the A320, then the A245 to Painshill to use the A3 southbound to rejoin the M25 at junction 10.

M25 Junction 10 to Junction 11 Closure Diversion Map